Construction Updates:
Need Assistance? Don't hesitate to reach out, we are here to help!
Christina Palumbo Senior Customer Experience Concierge 519-658-6656 Ext. 225 concierge@heritagehomes.com |
Update: March, 2023
Construction continues to progress at West Oak in Kitchener. We're looking forward to welcoming our final homeowners later this spring.
Update: November, 2022
West Oak remains busy as we work on completing the remaining blocks. This fall, we are working to complete landscaping work in Phase 1 while driveways and sidewalks will also be completed in Phase 2.
Update: August, 2022
West Oak remains active and busy with construction progress! Presently there are 5 blocks consisting of 38 units under construction.
Update: June, 2022
Framing is complete on the final 2 blocks and occupancies will continue through this summer as this community gets closer and closer to completion.
Update: May 2022
Framing is in progress on the remaining 2 blocks at West Oak and 7 out of 15 blocks are now occupied.
Update: April 2022
Our teams have been busy at West Oak! Registration of the first phase of the condominium has now taken place and the second phase of occupancy is expected to continue through the summer of 2022.
Update:March 2022
West Oak remains very busy as work continues to progress all through the community.
Update: January 2022
West Oak is a very busy community. All foundations are now in and framing is in progress for the final blocks. There is work going on all through the community from framing to finishing touches.
Update: November 2021
Construction continues to progress at West Oak. Closings have begun and more and more units are getting their brick.
Update: September 2021
Update: August 2021
Construction continues to progress at West Oak.
Update: June 2021
We have come to an exciting milestone at West Oak. We've poured 11 foundations and these blocks are well on their way to being completed! These blocks are all included in Phase 1 of construction at West Oak. There was a celebration to thank our trades and staff for all of their hard work. This is a busy community and it is only going to get busier in the weeks and months ahead.
Update: April 2021
We've compiled some resources below based on some frequently asked questions.
We know you're excited about your new purchase and we're here to guide you along in the process.
We hope we get to know more about you through your home building journey, but we'd like to start by putting a face to the name and telling you a little bit about ourselves. CLICK HERE to learn more about our Customer Experience team.
Update: March 2021
We are now well into 2021 and we wanted to provide you with an update on what's been happening at West Oak.If you have driven by West Oak over the past couple of weeks, you would have noticed a lot of activity going on. We are well on our way to seeing West Oak come out of the ground. At this time, foundations are being dug, footings are being poured and so much more!
Decor Selections
Decor appointments are currently being scheduled. If you haven't heard from your Decor Consultant yet, please be patient as our team meets with everyone that has purchased at West Oak. Start dreaming about what you would like the inside of your condo to look like!!
We will continue to provide milestone updates throughout this project, but in the meantime, please do not hesitate to contact us if you have any questions.